Free 2,500+ PMP questions for practice

To practice your pre-exam and review each question with detail explanation, let try with our FREE Exam tool

New matching, multiple choices exam questions from domain, process, business environment and agile which align with the new 2021 exam contain outline

New PMP Question & Answers with explanation

Directing project work on an agile project consists of several steps. Match the following steps with their descriptions.

Matching
Directing agile teamwork
Steps Description
Second Step
Review meetings are held to examine the work of the iteration and provide and receive feedback.
Fourth Step
The product backlog is defined.
First Step
Retrospectives are held at the end of the iteration to determine what went well, what improvements can be made to the process, and what didn't go well.
Fifth Step
Planning meetings are held at the beginning of the iteration to pull user stories into the iteration backlog
Third Step
Daily stand-ups are conducted to examine what was worked on yesterday, what will be worked on today, and what obstacles are standing in the way.

Match the following scaling agile frameworks with their description.

Matching
Scaling agile frameworks
Framework Description
Less
Two or more Scrum teams work on the project together. Each Scrum team focuses on a portion of the work.
Safe
This consists of up to eight Scrum teams with up to eight members each who all work on the project together.
Enterprise Scrum
This extends Scrum practices to all aspects of the organization.
Scrum of Scrums
This combines several agile best practices and includes information from functional areas of the business.
DA
This is an interactive knowledge base consisting of technical guidance, knowledge, and information on agile.

Match the following types of tests that are used on agile-based software projects to their description.

Matching
Testing at all levels
Name of test Description
End to end test
Testing the software from the start to the end to ensure the application is working correctly.
Smoke test
A high-level test designed to identify simple failures that could jeopardize the software program.
Regression test
This test is performed after changes are made to the code or when maintenance activities are performed on the hardware the code resides on to ensure the software works the same way it did before the change.
Integration test
This test combines software modules and tests them as a group.
Unit test
This test is performed on individual modules or individual components of source code.

Match the following agile measurements with their definitions.

Matching
Agile measurements and definitions
Agile measurements Definitions
Definition of done
A type of in-the-moment measure
Lead time
Typically expressed as deliverables, functionality, or features
Empirical measure
The time it takes to complete work on a task from the time work starts
Definition of ready
A checklist of elements needed to ensure the deliverable is ready for the customer to use
Response time
Describes the specifics of the tasks planned for the iteration before the team begins work
Cycle time
The time it takes for a task to go from request to completion
Capacity measures
The time a task waits before work starts
You are the project manager for a top-secret software project for an agency of the U.S. government. Getting top-secret clearances for contractors takes quite a bit of time and waiting for clearances could jeopardize the implementation date. Your mission—should you choose to accept it—is to complete the project using internal resources. Your agile programmers are 80 percent of the way through the programming and testing when your agency appoints a new executive director. Your programmers are siphoned off this project to work on the executive director's hot new project before they finish this project. Which of the following are true regarding this question?
Select two