100 New PMP Schedule Questions & Answers with explanation
Following is an illustration of a project network activity node that includes some information about activity D. Given the information provided, what is the total float of activity D?
The following table is an activity list that includes the duration and predecessor for a series of project activities. What is the duration of the critical path?
With reference to the diagram below, it can be inferred that the project is currently:
With reference to the diagram below, it can be inferred that the project is currently:
If a project has a To Cost Performance Index (TCPI) of 0.90, this means that: