100 New PMP Schedule Questions & Answers with explanation

1.

Following is an illustration of a project network activity node that includes some information about activity D. Given the information provided, what is the total float of activity D?


Select one
2.

The following table is an activity list that includes the duration and predecessor for a series of project activities. What is the duration of the critical path?


Select one
3.

With reference to the diagram below, it can be inferred that the project is currently:


Select one
4.

With reference to the diagram below, it can be inferred that the project is currently:


Select one
5.
The Create WBS process identifies the deliverables at the __________ level in the Work Breakdown Structure (WBS).
Select one
6.

If a project has a To Cost Performance Index (TCPI) of 0.90, this means that:

Select one
7.
The project manager and the team decide that the project will be divided into five-week iterations with two weeks in between for retrospectives and iteration planning. Where is this documented?
Select one
8.
In a pharmaceutical project, human trials are to start soon. The CEO is thrilled about the success of the trials up to this point. She announces that the size of the patient pool for the trials should double from the one originally planned and results tracked in the new system launching this week. What should the project manager do first?
Select one
9.
You are the project manager for the construction of a new thin-crust pizza vending machine. You take all the information gathered in the project management plan to date and begin to develop a project schedule. When you reach the activity labeled as 6.5.3, you are unsure if a refrigeration specialist is needed for the installation of the cooling mechanism for the pizza dough. What project document would you reference in order to get information on the resources required for installing the cooling mechanism?
Select one
10.
You and your team have compiled your project’s activity list, determined how the activities should be performed and analyzed the schedule. You are preparing information for the project sponsor to highlight the identified activities that may create a delay in the overall project schedule. Which of the following would be most useful in this situation?
Select one