A small sample of your project’s critical path is shown in the following table. Assuming each activity must finish before the next activity can begin, which of the following options is not correct?
Activity | Duration | Early Start | Early Finish |
1 | 22 | 5/1 | 5/22 |
2 | 5 | 5/23 | 5/28 |
3 | 7 | 5/9 | 6/4 |
4 | 1 |
A small sample of your project’s PERT calculations is shown here. Activity 2 is particularly important to the project, and your stakeholders are asking for a confidence level for this activity. You tell them there is a 95.44 percent chance of completing activity 2 within how many days?
Activity | Optimistic | Pessimistic | Likely Expected Value |
1 | 10 | 14 | 12 |
2 | 20 | 30 | 23 |
3 | 3 | 3 | 3 |
A small sample of your project’s PERT calculations is shown here. What is the total duration of the project?
Activity | Optimistic | Pessimistic | Likely Expected Value |
1 | 10 | 14 | 12 |
2 | 20 | 30 | 23 |
3 | 3 | 3 | 3 |