Free 1,400+ PMP questions for practice

To practice your pre-exam and review each question with detail explanation, let try with our FREE Exam tool

1,439 PMP Questions & Answers with explanation

1.
During the development of the project stakeholder engagement plan, a project manager is usually dependent on the voice of the project stakeholders to obtain expert opinion. Which of the following is an important tool available to the project manager for gathering and organizing stakeholders’ information?
PMBOK 6th edition - Page 511
2.
During which of the following project processes do key stakeholders engage with the project for the first time?
PMBOK 6th edition - Page 80
3.
Which of the following components of a project scope statement is useful in reducing scope creep?
PMBOK 6th edition - Page 154
4.
As you create the Activity List, which technique is recommended for subdividing the project into smaller components called activities?
PMBOK 6th edition - Page 185
5.
During the development of the project stakeholder engagement plan, the project manager is usually dependent on the expert judgment of senior stakeholders to identify and plan effective stakeholder management strategies. Which of the following stakeholders cannot guide the project manager in developing effective strategies for internal stakeholders?
PMBOK 6th edition - Page 550
6.
The Create WBS process identifies the deliverables at the __________ level in the Work Breakdown Structure (WBS).
PMBOK 6th edition - Page 157
7.
What is the primary risk when including reserves, or contingency allowances, in your cost estimate?
PMBOK 6th edition - Page 245
8.
Which of the following statements most accurately describes a project scenario?
PMBOK 6th edition - Page 549
9.
Which of the following is not an organizational process asset used during the Plan Resource Management process?
PMBOK 6th edition - Page 315
10.
During the Manage Stakeholder Engagement process, a number of project documents might get updated. Which of the following project documents get updated the most during this process?
PMBOK 6th edition - Page 529
Hover for Answers: