New PMP Question & Answers with explanation
Two efficiency indicators that reflect the cost and schedule performance of a project are:
Select one
If the project's current total earned value (EV) is $100,000 and the actual amount spent (AC) is $95,000, what is the cost variance of the project?
Select one
If you are managing changes to the project's cost baseline, which process are you using?
Select one
What is the primary risk when including reserves, or contingency allowances, in your cost estimate?
Select one