89 New PMP Procurement Questions & Answers with explanation

1.
The project sponsor is concerned about possible ethics violations between the project and vendors. What independent review can the sponsor order?
Select one
2.
You are conducting the source selection analysis for an office building renovation project. One project requirement involves setting up the WiFi system once the hardware has been installed. The value of this procurement is relatively small, and you have decided that a full selection process does not make sense. With three prospective vendors listed as pre-approved sellers, what is the best course of action?
Select one
3.
Services are still being billed to the project even though no additional services are required or requested. What is the best option for the project manager to take?
Select one
4.
As a project manager for a small university, you are currently in the process of selecting a vendor to develop a textbook and other training materials for a new course. Several vendors are interested in bidding on the contract. During a bidder conference, one of the prospective suppliers asks about ownership of the intellectual property that will be created from the project. Which project document should have this information at this stage of the project?
Select one
5.
A team member has been tasked to send the request for proposal (RFP), source selection criteria, and procurement statement of work (SOW) to potential sellers. The documentation is stored digitally on the corporate computer network. Which folder from the project directory is most likely to include these documents?
Select one
6.
During a bidder conference, a supplier asks why a section is missing from the request for quotation (RFQ). The project manager, realizing that an aspect of the project is indeed missing, becomes flustered and stumbles through a brief reply. When the seller responses were received, all but three fail to address the missing section. What is the best course of action?
Select one
7.
You have completed a nine-month project, and you are in the closing stage. The project completed on time and under budget and everyone in your department has congratulated you on your achievement. The vice president of your company heard about the success of your project and wants a summary overview of project performance so that he can talk about your success at the next board meeting. What should you provide to him?
Select one
8.
You are leading a project to build an oil pipeline in a foreign country, and you are looking for local contractors to outsource some of the construction work. You are in the process of preparing the bid package for prospective sellers. Which of the following documents would you leave out of the package?
Select one
9.
A company manages SBG contracting bids for government tenders and all successful bids as a separate project. The structure of the company is mainly projectized for a dedicated project team to manage each project. However, to realize economies of scale, there are some central departments that serve all projects. Which of the following role is most likely to be working in a central department instead of directly working with a project team?
Select one
10.
Crashing is an effective schedule compression technique at times when a project is struggling behind schedule. However, increasing the number of resources to twice the original number of the resources does not always cut the time by half. This is due to:
Select one