New PMP Question & Answers with explanation
After the kick-off meeting, the project manager notices that to deliver the system, the team must implement new hardware within the next three months. The procurement team notifies the project manager that the current suppliers need at least three months' notice to deliver this type of system. Worried about the risk to delivery dates, the project manager begins looking for alternative suppliers that adhere to their company's procurement policy. What risk response strategy did the project manager use?
Select one