A project manager needs to outsource 1,200 resource hours. Due to internal policies, each provider must understand the requirements. What should the project manager do to ensure this?
Select one
A supplier has been awarded a firm fixed price (FFP) contract to provide various materials for a construction project. The contractor has received all pertinent documents relating to material standards and specifications. By contract, the supplier must deliver all materials to the construction site on a specific date. When the materials arrive at the site on time, what should the project manager do?
Select one