New PMP Question & Answers with explanation

A project manager is working on a project for which the project sponsor is also the customer. Since the project is running smoothly, the sponsor/customer asks that the project manager send status reports only if the project is in trouble. What should the project manager do?
Select one
A project manager leads a complex project with stakeholders located in several countries. The project manager learns that a senior manager asked a team member for project information. What should the project manager do next?
Select one