New PMP Question & Answers with explanation
A project manager learns that, due to supplier delays, task I should start 10 days after the start of task H. The project manager produces a network diagram where each task has a three-day duration, and re-evaluates the critical path. What is the new critical path?
Select one
There are three main tasks in a new product development project. Task A must be delivered two weeks before task C starts, and task C will start once task B is finished. What is the relationship between tasks A and B?
Select one
A project's statement of work (SOW) requires that the project be delivered in six months. The project manager is concerned that the timeline is unreasonable. What should the project manager do to address this?
Select one
A project manager is developing the schedule management plan for a data center migration project. The project sponsor asks for a schedule that plans all tasks as soon as possible. The project manager is presented with possible network paths that will not violate schedule constraints. What leads and lags relationship should the project manager select?
Select one
A project manager is uncertain about the duration of a new product and consults several groups of subject matter experts (SMEs). The first group advises that development can be finished in 30 days. The second group identifies some risks that could make the duration up to 45 days. The third group proposes a new development method that can shorten the time to 21 days. What is the estimated development duration for the new product?
Select one