2,934 New PMP Id 1028 project management is concerned with managing which type of project Questions & Answers with explanation

1301.
You are in the Planning stage of the project and have just begun to generate the cost baseline. In what activity are you engaged as a project manager?
Select one
1302.
During this contract life-cycle phase, the vendors are asked to compete for the contract and respond to the RFP. What contract life-cycle phase is this?
Select one
1303.
A project manager has facilitated the decomposition of work packages into activities. She next carries the team through several exercises to sequence the activities and determine what and how many resources will be needed to perform the work. What is she likely to do next?
Select one
1304.
You are a project manager and are in the stage of the project where you are juggling a lot of activities at the same time. You are negotiating for resources, negotiating procurements, and monitoring risks and risk triggers. An approved change request has come your way and must be processed back through this process. This approved change will expand your project scope. You daydream of escaping the day-to-day work life and for a brief moment wonder whether you could contract this additional work through your spouse’s company and take the money and run. But then the daydream bubble bursts and it’s back to reality. What process does this describe, and what area within the PMI Code of Ethics and Professional Conduct pertains to this situation?
Select one
1305.
Several processes in the Monitoring and Controlling process group involve change requests. Which of the following is not true?
Select one
1306.
A project manager meets with a key set of experts within her project team. They express concerns over a recent scope change that was submitted by the customer, since the project is deep into the execution stages of the project life cycle. Which of the following is a valid technique that can aid the project manager in addressing the team’s concerns?
Select one
1307.
You’re a project manager for Music On Demand, and you’re in the Monitor Risks process. Your project, when completed, will provide a way for owners of smartphones to purchase music on demand from the recording company you work for and download it directly to their devices. You are monitoring the risks on the project and have analyzed elements such as the risk audits, preventive actions, and corrective actions. This information might be reported in which of the following outputs of this process?
Select one
1308.
Which of the following reflect principles listed in the Agile Manifesto?
Select three
1309.
A project manager is likely to leverage the following techniques to manage stakeholder engagement except for which one?
Select one
1310.
Your selection committee can choose only one of the following projects: Project A’s original investment is $1 million, the present value of the cash inflows is $1 million, and the discount rate is 4 percent. Project B’s original investment is $1.4 million, the present value of the cash inflows is $1.4 million, and the discount rate is 6 percent. Project C’s original investment is $1.8 million, the present value of the cash inflows is $1.8 million, and the discount rate is 7 percent. Which project should the committee choose?
Select one