2,934 New PMP Id 1028 project management is concerned with managing which type of project Questions & Answers with explanation
1971.
Lucy has recently been assigned as the project manager for a new shopping mall construction project. Since the project will span well over five years, Lucy is a bit hesitant to use the current market rates for estimating construction materials cost. The prices have been steadily increasing and the current market rates might not remain valid in the future. Which of the following techniques can Lucy apply to determine her project budget?
Select one
1972.
You are attempting to estimate the resources required to assemble the server racks in the new data center you are building. It has occurred to you that you may be able to compress the schedule if you use power tools instead of hand tools to build the racks and if you employ individuals who have worked on this brand of rack in the past. According to PMBOK, considering multiple options for estimating is an example of what type of resource estimating technique?
Select one
1973.
You have just received an invoice from your supplier that contains some uncertified items. Payments to the supplier are processed through your corporate accounts payable system only after certification of satisfactory work by the project quality control specialist. What should you do?
Select one
1974.
All of the following statements are true about the cause-and-effect diagram except:
Select one
1975.
You are the project manager for Commodities, Inc. You are involved in a new project to create an internal website for the employees that will allow them to view events within the company. All of the following options listed are project constraints except:
Select one
1976.
In a small office construction project, the following activities are scheduled in sequence. i) Digging and pouring footings: five days. ii) Working on the slab and pouring: three days. iii) Framing the floor: five days. iv) Wall framing: four days. v) Roof framing: six days. vi) Insulation and drywall: seven days. vii) Interior doors and trim: three days. viii) Hardware and fixtures: two days. What is the minimum time to complete the project if all activities are on a critical path except activity viii, and activity iii is delayed by one day?
Select one
1977.
During the execution of a project, the project manager discovers the project’s stakeholder register is no longer accurate. What should the project manager do?
Select one
1978.
In a ship design project, a project manager is in the process of negotiating with a consulting company to ensure that the project receives certified and specialized consultants for creating the hull design. The project manager wants to make certain that the consultants will be able to work until their assignments are completed. He is using all his negotiation skills and interpersonal skills to get competent staff on time. Based on the scenario described above, the project manager is engaged in:
Select one
1979.
The Stakeholder Committee has a report that shows zero schedule variance. However, the first milestone in the project was missed, which will cause a delay in the project. Which of the following was not reported correctly?
Select one
1980.
The organization's safety and health policy, ethics policy, project policy, and quality policy can be used by a project to influence its success. All these policies are a part of:
Select one