New PMP Question & Answers with explanation
A project manager joins a project that has just started. The sponsor and project team assure the new project manager that the project has an adequate budget and realistic schedule. The project manager is concerned about unplanned events that could threaten the project's success. What should the project manager do?
Select one
After the kick-off meeting, the project manager notices that to deliver the system, the team must implement new hardware within the next three months. The procurement team notifies the project manager that the current suppliers need at least three months' notice to deliver this type of system. Worried about the risk to delivery dates, the project manager begins looking for alternative suppliers that adhere to their company's procurement policy. What risk response strategy did the project manager use?
Select one