205 New PMP Agile scrum Questions & Answers with explanation

181.
A project manager is leading a project with team members dispersed globally. Which of the following tools or methods can the project manager use to create virtual workspaces?
Select two
182.
All of the following are characteristics of the Agile life cycle except for which one?
Select one
183.
Nicolas is the project manager of a project that has been described as revolutionizing the mobile fitness tracking industry. He prepares for a meeting with the project’s sponsor to discuss how to approach the project. During the meeting, he tells the project sponsor that he would like to promote self-awareness, listening, and coaching versus controlling. Nicolas is promoting characteristics of what?
Select one
184.
The project manager and the team decide that the project will be divided into five-week iterations with two weeks in between for retrospectives and iteration planning. Where is this documented?
Select one
185.
In a pharmaceutical project, human trials are to start soon. The CEO is thrilled about the success of the trials up to this point. She announces that the size of the patient pool for the trials should double from the one originally planned and results tracked in the new system launching this week. What should the project manager do first?
Select one
186.
Your company was recently awarded a software development project, and you have just completed the scope management plan. The sponsor reviews the plan and states that the client specified the use of Scrum, while the plan indicates a waterfall approach. Which component of the project management plan did you most likely overlook while developing the scope management plan?
Select one
187.
You are leading a project to develop a new web application. Together with your project team you reprioritize the product backlog, determine velocity for the past iterations, and adapt your work plans accordingly. Additionally, you facilitate retrospectives every two weeks. Which of the following processes describes the work you are performing?
Select one
188.
Which of the following is an agile prototyping technique showing sequence or navigation through a series of images or illustrations:
Select one
189.
Which of the following is an example of a chart, used on agile projects, that tracks the work that remains to be completed in the iteration backlog?
Select one
190.
Which of the following approaches deliberately spends less time trying to define and lock project scope early during the project and spends more time establishing the process for requirements gathering, scope definition and refinement?
Select one