- Project Management Plan
- Change Management Plan
- Project Roadmap
- Scope Management Plan
- Requirements Management Plan
- Requirements Documentation
- Requirements raceability Matrix
- Project Scope Statement
- Work Breakdown Structure
- WBS Dictionary
- Schedule Management Plan
- Activity list
- Activity attributes
- Milestone list
- Network diagram
- Duration estimates
- Duration estimates worksheet
- Project schedule
- Cost management plan
- Cost estimates
- Cost estimating worksheet
- Cost baseline
- Quality management plan
- Quality metrics
- Responsibility assignment matrix (RAM)
- Resource management plan
- Team charter
- Resource requirements
- Resource breakdown structure
- Communications management plan
- Risk management plan
- Risk register
- Risk report
- Probability and impact assessment
- Probability and impact matrix
- Risk data sheet
- Procurement management plan
- Procurement strategy
- Source selection criteria
- Stakeholder engagement plan
Cost estimating worksheet
A cost estimating worksheet can help to develop cost estimates when quantitative methods or a bottom- up estimate are developed. Quantitative methods include:
- Parametric estimates
- Analogous estimates
- Three-point estimates
Parametric estimates are derived by determining the cost variable that will be used and the cost per unit. The number of units is multiplied by the cost per unit to derive a cost estimate.
Analogous estimates are derived by comparing current work to previous similar work. The size of the previous work and the cost are compared to the expected size of the current work. Then the ratio of the size of the current work compared to the previous work is multiplied by the previous cost to determine an estimate. Various factors, such as complexity and price increases, can be factored in to make the estimate more accurate. This type of estimate is generally used to get a high-level estimate when detailed informa- tion is not available.
A three-point estimate can be used to account for uncertainty in the cost estimate. Stakeholders pro- vide estimates for optimistic, most likely, and pessimistic scenarios. These estimates are put into an equa- tion to determine an expected cost. The needs of the project determine the appropriate equation, though a common equation is a beta distribution:
Estimated cost = | Optimistic Cost + 4 (Most Likely Cost) + Pessimistic Cost |
6 |
Bottom-up estimates are detailed estimates done at the work package level. Detailed information on the work package, such as technical requirements, engineering drawings, labor duration, and other direct and indirect costs are used to determine the most accurate estimate possible.
The cost estimating worksheet can receive information from:
- Cost management plan
- Scope baseline
- Project schedule
- Quality management plan
- Resource requirements
- Risk register
- Lessons learned register
Cost estimating worksheets are process 7.2 Estimate Costs in the PMBOK® Guide – Sixth Edition.
Cost estimating worksheets are developed and then refined as periodically as needed.
Document element | Description |
ID | Unique identifier, such as the WBS ID or activity ID |
Parametric estimates | |
Cost variable |
Enter the cost estimating driver, such as hours, square feet, gallons, or some other quantifiable measure. Example: Square feet |
Cost per unit |
Record the cost per unit. Example: $9.50 |
Number of units |
Enter the number of units. Example: 36 |
Cost estimate |
Multiply the number of units times the cost per unit to calculate the estimate. Example: $9.50 x 36 = $342 |
Analogous estimates | |
Previous activity |
Enter a description of the previous activity. Example: Build a 160 square foot deck. |
Previous cost |
Document the cost of the previous activity. Example: $5,000 |
Current activity |
Describe how the current activity is different. Example: Build a 200 square foot deck. |
Multiplier |
Divide the current activity by the previous activity to get a multiplier. Example: 200/160 = 1.25 |
Cost Estimate |
Multiply the cost for the previous activity by the multiplier to calculate the Cost Estimate for the current activity. Example: $5,000 x 1.25 = $6,250 |
Three-point estimate (beta distribution) | |
Optimistic cost |
Determine an optimistic cost estimate. Optimistic estimates assume all costs were identified and there won’t be any cost increases in material, labor, or other cost drivers. Example: $4,000 |
Most likely cost |
Determine a most likely cost estimate. Most likely estimates assume that there will be some cost fluctuations but nothing out of the ordinary. Example: $5,000 |
Pessimistic cost |
Weight the three estimates and divide. The most common method of weighting is the beta distribution, where c = cost: cE = (cO+ c4M + cP)/6 Example: (4,000 +4 (5,000))/6 |
Expected cost |
Enter the expected cost based on the beta distribution. Example: $5,250 |
Elements of a bottom-up cost estimating Worksheet
Document element | Description |
ID | Unique identifier, such as the WBS ID or activity ID |
Labor hours | Enter the estimated effort hours. |
Labor rate | Enter the hourly or daily rate. |
Total labor | Multiply the labor hours times the labor rate |
Material | Enter quotes for material, either from vendors or multiply the amount of material times the cost per unit. |
Supplies | Enter quotes for supplies, either from vendors or multiply the amount of supplies times the cost per unit. |
Equipment | Enter quotes to rent, lease, or purchase equipment. |
Travel | Enter quotes for travel. |
Other direct costs | Enter any other direct costs and document the type of cost. |
Indirect costs | Enter any indirect costs, such as overhead. |
Reserve | Enter any contingency reserve cost for the work package. |
Estimate | Sum the labor, materials, supplies, equipment, travel, other direct costs, indirect costs, and any contingency reserve. |