2,934 New PMP Id 1028 project management is concerned with managing which type of project Questions & Answers with explanation
1791.
A project manager has just taken over the project from another project manager during project executing. The previous project manager created a project budget, determined communications requirements, and went on to the complete work packages task. What should the new project manager do next?
Select one
1792.
A data point on a control chart that requires investigation is called
Select one
1793.
A project manager is gathering data with the team to determine how various factors might be linked to potential problems. In what part of the quality management process is the project manager working?
Select one
1794.
All the following are tools of control quality except:
Select one
1795.
Five of the seven phases on the project contain work that is substantically similar. What must the project manager do?
Select one
1796.
Which of the following is an output of the plan quality management process:
Select one
1797.
While testing the strength of concrete poured on your project. You discover that over 35 percent of the concrete does not meet your company`s quality standards. You feel certain the concrete will function as it is, and you don't think the concrete needs to meet the quality level specified. What should you do?
Select one
1798.
A project manager and team from a firm that designs railroad equipment are tasked to design a machine to load stone onto railroad cars. The design allows for 2 percent spillage, amounting to over two tons of spilled rock per day. In which of the following does the project manager document quality control, quality assurance and quality improvements for this project?
Select one
1799.
All of the following are parts of the control quality process except
Select one
1800.
A project manager takes over an existing project, only to find that there are no quality standards. What part of the quality process should the project manager be in
Select one