2,934 New PMP Id 1028 project management is concerned with managing which type of project Questions & Answers with explanation

1851.
Estimate at completion (EAC) is a periodic evaluation of:
Select one
1852.
Monitoring cost expended to date in order to detect variances from the plan occurs during:
Select one
1853.
You have estimated the project cost to be us $850k within -25/+75 percent of actual. This is a
Select one
1854.
The cost contingency reserve should be:
Select one
1855.
Your project has a AC = $800million, PV = $890millions, and a CPI = 1.1. How is the project going?
Select one
1856.
Cost performance measurement is best done through which of the following?
Select one
1857.
Your cost forecast shows that you will have a cost overrun at the end of the project. Which of the following should you do?
Select one
1858.
What would be the best explanation for the following: both the cost variance and schedule variance are negative, but the cost variance is lower than the schedule variance
Select one
1859.
Your organization is hoping to meet its strategic objective to grow the business by expanding to foreign markets. Since working with international sellers is new to you as a project manager you are researching potential issues others have encountered on international projects. You have learned of situations where issues have arisen due to illegal payments. Which e following payments on an international project is unacceptable?
Select one
1860.
Which of the following defines things the project manager needs to do regarding cost
Select one