New PMP Question & Answers with explanation

Cost performance measurement is best done through which of the following?
Select one
Although the stakeholders thought there was enough money in the budget, halfway through the project the cost performance index (CPI) is 0.7. To determine the root cause, several stakeholders audit the project and discover the project cost budget was estimated analogously. Although the activity estimates add up to the project estimate, the stakeholders think something was missing in how the estimate was completed. Which of the following describes what was missing?
Select one
Your cost forecast shows that you will have a cost overrun at the end of the project. Which of the following should you do?
Select one
What would be the best explanation for the following: both the cost variance and schedule variance are negative, but the cost variance is lower than the schedule variance
Select one
You have always been asked by your management to cut your project cost estimates by 10 percent after you submitted them. The scope of your new project is unclear, and there are over 30 stakeholders. Management expects a 25 percent reduction in downtime as a result of the project. Which of the following is the best course of action in this situation?
Select one