2,934 New PMP Id 1028 project management is concerned with managing which type of project Questions & Answers with explanation

2101.
Which of the following is a type of leadership style in which leaders are hands-off and allow group members to make the decisions:
Select one
2102.
Your project team is having a dispute with a vendor about whether a specific task is within the project’s scope. The scope statement does not provide implementation-level details that could resolve this dispute. There is no WBS, however, because the project sponsor insisted that the project be started right away without pausing to create standard project planning documentation. Who is at fault?
Select one
2103.
For a project following a predictive life cycle, which of the following statements is most accurate?
Select one
2104.
Which of the following is one of the most prominent features of a project following agile approach for product development?
Select one
2105.
You are the project manager for a Fortune 100 IT company, and you are currently engaged in an important project. You want to choose the best contractor for a specialized task. What should you do to evaluate potential contractors?
Select one
2106.
Acceptance is a strategy adopted because it is not possible to eliminate all risks from a project. This strategy indicates that the project management team has decided not to change the project management plan to deal with a risk. What action does passive acceptance require?
Select one
2107.
A buyer and seller set the rates for junior engineers, senior engineers, architects, and other predefined roles. In what type of contract would this be applicable?
Select one
2108.
A project manager is estimating project costs and needs to decide whether the estimates will include direct costs only or include indirect costs, as well. In which of the following phases does this decision need to take place?
Select one
2109.
After conducting a bidder conference, you receive an email from one of the bidders requesting additional information. The information was neither included in your request for proposal, nor did anyone ask for it during the bidder conference. You realize the answer to this question is critical to understanding the scope of the project. If the answer is not communicated to bidders, they cannot size their teams accurately or estimate the total duration of the project. The answer also greatly affects cost. However, the answer contains some proprietary information that, if disclosed to a competitor, may reveal the future product strategy of your company. Such a disclosure could be disastrous for a major product launch you are planning next year. You decide to send the answer to all the bidders, but you realize one of the bidders is also working closely with one of your competitors on a similar project. What should you do?
Select one
2110.
During a project status meeting, a project manager presented sensitive information related to the project. However, this information was not intended to be available to the audience. Which of the following processes was done incorrectly, resulting in the project manager communicating sensitive information to the wrong audience?
Select one