2,934 New PMP Id 1028 project management is concerned with managing which type of project Questions & Answers with explanation

2111.
In an underground highway construction project, the project stakeholders have suggested many changes to the project scope. You had already defined the cost baseline in your project, and you would like to revisit the baseline to see how these changes might affect the overall cost of the project. You start an impact analysis to determine the impact and inform the concerned stakeholders of all approved changes and the corresponding costs. You perform these activities in which process?
Select one
2112.
You have been managing a research project to create genetically modified fruits using genetic engineering techniques. Since many legal issues are involved in this process, you created contingency allowances by using various quantitative analysis methods to account for cost uncertainty. You have just concluded a brainstorming session with your team in the execution phase to monitor risks that have developed in the project over the past few weeks and to establish new risk response plans. What should you do if you want to allocate more contingency reserves to account for new risks?
Select one
2113.
Diana is managing the development of a mobile phone application. Half the project work has been completed. Diana is currently reviewing her stakeholder engagement plan. She finds that some of the resisting stakeholders have now become supportive. How should Diana update her stakeholder engagement plan?
Select one
2114.
Lesley is managing a software development project for the World Climate Control Organization. Since her team members are dispersed across the globe, she would like to set up online conferences in the next two months to let everyone in her project know what is going on and what their roles are within the project. She wants to use these conferences as team development activities to learn and exchange information in the project. To schedule such activities, which of the following should she use to keep track of the availability of team members?
Select one
2115.
Nancy can bid on two projects. Project A has a 50 percent return on investment while Project B has a 20 percent return on investment. Project A’s scope of work is complex, and Nancy’s organization does not have the necessary skills and experience to do this project. However, Project B’s scope of work falls within the strengths of Nancy’s organization. Which project must Nancy bid on?
Select one
2116.
Mary is a project manager for an infrastructure upgrade project in a government agency. She realized recently that a critical scheduled task exceeded its deadline, and the stakeholders are aware of it. The resource manager has permitted Mary to use three more resources to work on and complete the delayed task. Although the three additional resources prove helpful, Mary is still concerned about the task because:
Select one
2117.
You have recently started working as a project manager for a health insurance portal development project. The project sponsor tells you that due to the critical nature of the project, the work must start immediately and complete in two weeks. Based on the instructions, you have started documenting significant constraints and assumptions to perform the project feasibility study. What should you do if you can prepare only the high-level feasibility study in the given time frame?
Select one
2118.
You are using parametric estimating techniques to estimate costs for each activity and the total budget in your project. However, a project manager colleague tells you to bump up each estimate by 20 percent to account for any unknown risks, and then submit that as a total budget to the customers. What should you do?
Select one
2119.
You have recently taken over a project from a PMP-certified project manager who was removed from the project due to incompetence and lack of skills. When you happen to meet him outside your building, he starts rebuking you for taking his project. He even goes so far as to suggest that your religion played a part in your selection by the management. What should you do first?
Select one
2120.
A project manager has completed identification of stakeholders and has started planning for a flow instruments installation project in a hospital. While developing the project management plan, a team member states that a stakeholder in the X-ray department is missing from the stakeholder list. Which of the following would be the best response from the project manager?
Select one