2,934 New PMP Id 1028 project management is concerned with managing which type of project Questions & Answers with explanation

2631.
Sarah is about to start developing her project stakeholder engagement plan. She is currently gathering all the required inputs for this process. She has already created the stakeholder register and has gotten access to the organizational process assets and enterprise environmental factors. Which of the following inputs is also critical for the process?
Select one
2632.
Product scope is measured against the product requirements, while project scope is measured against:
Select one
2633.
In the procurement process, the seller may be viewed initially as a bidder, then as the selected source, and then as the contracted supplier. The seller will typically manage the work as a project. In such an instance, which of the following is not true?
Select one
2634.
The product design your project team developed was extremely well received by the customer. There were two key contributors to this design. The customer calls you to tell you how pleased he is with the design. What do you tell him?
Select one
2635.
Lucy is managing a complex design-and-build project. Stakeholder involvement and influence have been significant since the project’s inception. Under such circumstances, the Monitor Stakeholder Engagement process should be:
Select one
2636.
You just initiated a project to establish windmills in a developing country. To celebrate the initiation of the project, the customers arranged a party in which a key customer offered valuables to you and all your project team members with a request to complete the project sooner than the actual finish date. What should you do?
Select one
2637.
You overlooked a high-level risk in an insurance project and failed to document it in the project charter. If the risk shows up during the planning phase, what should be your response as a project manager?
Select one
2638.
You have recently started working as a project manager for a public school construction project. Your analysis shows that the cost estimate for the project seems to be unreasonable, and it could take at least 25 percent more funding to complete the project. What should you do if your sponsor wants to undertake the project with another project manager in case you refuse to accept it?
Select one
2639.
One of your team leaders informs you that a team member criticizes him constantly about the allocation of tasks. The team leader also asserts that this team member is also responsible for the delay of many tasks, leading to delays in the project schedule. What action should you take as a project manager?
Select one
2640.
What should you do as a senior project manager if the PMP certification claimed by a recently recruited project manager does not appear in the PMI website?
Select one