113 New PMP Integration Questions & Answers with explanation

91.
A project post-mortem is an activity, usually performed at the project’s conclusion, to determine and analyze a project’s outcome which also includes a lessons-learned gathering exercise. Project post-mortems help to mitigate future risks and are often a key component of, and ongoing precursor to, effective risk management. Which of the following is a terrible mistake when collecting lessons learned?
Select one
92.
A project manager calls you in as a consultant to provide input on developing the Project Charter. According to the PMBOK, your contribution to the project could best be termed as:
Select one
93.
Which process is concerned with providing forecasts to update current cost information?
Select one
94.
Which of the following would not be considered an Enterprise Environmental Factor during the Develop Project Charter process?
Select one
95.
The Close Project or Phase process is not performed when:
Select one
96.
Which of these tools and techniques is common to all seven Project Integration Management processes?
Select one
97.
Projects are often started as a result of an external factor such as market demand for a new product, a new legislative or regulatory mandate, or a change in technology. This results in the creation of ______ by an entity or organization external to the project.
Select one
98.
You are planning a storage device migration in a data center. During this phase of the project, who should control the project?
Select one
99.
All of the following are components of an effective change control process, except:
Select one
100.
A project manager was involved in preparation of the project charter for an external project. One of the inputs to the project charter was a statement of work (SOW). The SOW may have been received from the customer as part of any of the following except:
Select one