2,934 New PMP Questions & Answers with explanation

2431.
Establishing control accounts for the work packages and a unique identifier from a code of accounts finalizes the WBS. This provides a structure for hierarchical summation of:
Select one
2432.
Uncontrolled project scope changes are often referred to as ________ .
Select one
2433.
While managing a project, you have included the product acceptance criteria in the Quality Management Plan. While reviewing your plan, a senior manager asks you to reconsider this. You then realize that what you did is incorrect. Where should you place the product acceptance criteria?
Select one
2434.
The Project Scope Management Knowledge Area is primarily concerned with:
Select one
2435.
A project manager approaches you to understand the Work Breakdown Structure (WBS) in better detail. You tell her that:
Select one
2436.
An organization wishes to ensure that the opportunity arising from a risk with positive impact is realized. This organization should:
Select one
2437.
Your vice president asked you what the Estimate at Completion (EAC) will be for a small project you are working on. You were given a budget of $30,000, and to date you have spent $20,000 but only completed $10,000 worth of work. You are sure the future work will be accomplished at the planned rate. What is the EAC?
Select one
2438.
You just sat through an exhausting change control meeting discussing a change in scope to the project you have worked on for the past seven months. After lengthy discussion, the change in scope was approved. As the Project Manager, you should now update all the following documentation, except:
Select one
2439.
You work at a software company that authors Material Safety Data Sheets (MSDS) for chemical companies. Prior to releasing the MSDS to the company, you have created a list of items for review to ensure they appear in the document. These items include chemical name, CAS#, protection required, what to do in an emergency, etc. This list is an example of what type of tool?
Select one
2440.
Agile release planning provides a high-level summary timeline of the release schedule based on the project roadmap. Agile release planning also determines the number of iterations required for the product development. These iterations are also known as:
Select one