2,934 New PMP Id 1028 project management is concerned with managing which type of project Questions & Answers with explanation

1211.
You are a project manager for Community Trends, a nonprofit organization. Your project has come about because of a social need. So far, the project has experienced some cost variances, but these variances are atypical and are not expected to continue. You know the following information: BAC = 900, EAC = 885, PV = 475, EV = 500, and AC = 425. Which of the following is the correct ETC given this information?
Select one
1212.
The tools and techniques of the Acquire Resources process include all of the following except for which one?
Select one
1213.
You are the project manager for a pharmaceutical company. The latest project involves a new drug that will be released in six months. The project for the release is going well and closely mirrors the release of a drug that took place the previous year. With accurate historical information and quantifiable parameters in hand, what is the best type of cost estimating technique to use during the Determine Budget process?
Select one
1214.
Which of the following best describes the purpose of the project management plan?
Select one
1215.
The project sponsor asks the project manager to validate that the product scope has been met. What will the project manager use to measure the completion of the product scope?
Select one
1216.
You are using the tools and techniques of the Control Schedule process and know all of the following are true except for which one?
Select one
1217.
David is a project manager working for a prominent book publishing company. As the most senior project manager within the organization, he often gets the most complex project assignments. For this reason, the PMO manager assigns David to manage a project for a sponsor who is notorious for scope creep. Knowing this, David is likely to place greater emphasis on what project management process?
Select one
1218.
A project manager is managing a project working to produce a fitness tracking device. He has just finished getting the project authorized and analyzing stakeholder needs and expectations. What activity is he likely to perform next?
Select one
1219.
Carina is a principal project manager of You’ve Got Dogs, a specialty company that creates custom dog apparel and toys. She has just finished developing the project charter of a project that will create a new line of high-tech dog bones. What is the significance of the project charter?
Select one
1220.
Your organization uses a predicative approach to managing projects. You have recently kicked off your project, and you are beginning a series of overview sessions with key users to determine requirements for a new enterprise resource software implementation. What process group are the activities you are performing in?
Select one