2,934 New PMP Id 1028 project management is concerned with managing which type of project Questions & Answers with explanation

1621.
A project is underway to construct a 50 story office building. With construction nearly complete, a government inspector has issued a stop order because one of the cranes failed inspection. The schedule reserves are inadequate to cover the resulting delay from the unavailability of the key resource. What should the project manager do next?
Select one
1622.
A project manager has just learned that the customer is not showing up to requirements meetings saying they have other more important tasks. Since this behavior has already been identified as a risk earlier in the project, the project manager escalates the issue to the stakeholder who is the risk owner responsible for communicating with the customer in such situations. The stakeholder is shocked to find out she is the assigned risk owner. What most likely went wrong?
Select one
1623.
With a parking garage construction project underway, you are currently creating the risk management plan. In support of this process, you need to determine the acceptable level of overall project risk exposure. What should you do first?
Select one
1624.
A project team performs monthly risk audits for a project in which a large number of identified risks have been realized. So far, the risk responses have been appropriate, and reserves are sufficient. An executive for the requesting organization chides the project manager for doing risk audits improperly, stating that like all audits, outside independent resources need to perform risk audits. How should the project manager respond?
Select one
1625.
Your boss is giving you a rough outline of the scope, constraints, and risks involved in a prospective client's project. The project is highly similar to another project you are currently closing. The sponsor wants to know how long this project would take your team to complete. You think your team may need two months, but what should your answer be?
Select one
1626.
You are part of a cross-functional organizational development team, piloting an adaptive approach to project management in an organization that has traditionally used a predictive approach. You realize that you have to tailor the template of the schedule management plan. Which of the following components of the template are you likely to tailor the most?
Select one
1627.
You are leading a project to develop a new web application. Together with your project team you reprioritize the product backlog, determine velocity for the past iterations, and adapt your work plans accordingly. Additionally, you facilitate retrospectives every two weeks. Which of the following processes describes the work you are performing?
Select one
1628.
During a bidder conference, a supplier asks why a section is missing from the request for quotation (RFQ). The project manager, realizing that an aspect of the project is indeed missing, becomes flustered and stumbles through a brief reply. When the seller responses were received, all but three fail to address the missing section. What is the best course of action?
Select one
1629.
You are leading a project to construct a new runway at an existing commercial airport. After completion of the project, the residents under the flight path of the new runway are making noise complaints and want the airport to compensate them for the diminished values of their homes. What might you have missed earlier in the project?
Select one
1630.
As a project manager, you are leading a software development project where the developers are colocated within rented office space. Writing the code is taking longer than anticipated, and you have contacted the office facility to ensure the office will be available for another week. Unfortunately, the office is already booked, so you need to find another solution. After capturing the problem in the project documents, what should you do next?
Select one