2,934 New PMP Id 1028 project management is concerned with managing which type of project Questions & Answers with explanation
1601.
You and your team have compiled your project’s activity list, determined how the activities should be performed and analyzed the schedule. You are preparing information for the project sponsor to highlight the identified activities that may create a delay in the overall project schedule. Which of the following would be most useful in this situation?
Select one
1602.
You are a project manager for a new product development project that is in the planning stages. Your project team has just finished creating the activities list and is now in the process of identifying and documenting relationships among the project activities. While meeting with your project team, you notice that a series of activities can be done in parallel but must finish in a specific sequence. Your team is debating which type of activity sequencing method to use. What would you tell them?
Select one
1603.
A project manager is meeting with Sally, the program manager, to review the decomposed deliverables for a new product. Sally reviews the work breakdown structure and requests it to be arranged in the order the work should be performed. Is Sally correct saying that the work breakdown structure should be ordered according to how the work will be performed?
Select one
1604.
In a steering committee meeting for a project to build a new state-of-the-art communications device, the committee chair reprimands the project manager for not using the company’s file sharing system as required by the organization. The project manager explains that the project team chose a newer tool for the project, as it was much better. What most likely caused this situation?
Select one
1605.
A project manager is leading an infrastructure development project and is just starting the process of prioritizing individual project risks for further analysis. A stakeholder has expressed concern that the existing information about individual project risks may not be accurate and reliable. What is the best course of action?
Select one
1606.
A project manager is currently in the process of prioritizing individual project risks by assessing their detectability, proximity, and impact value. The project manager would like to create a graphical representation of these three dimensions. What is the best course of action?
Select one
1607.
A project is six months into its nine-month projected duration, and the project manager is reporting that the project is at least three months behind schedule because certain key stakeholders were resistant to any changes that might occur as outcomes of the project. What might have been done differently during project planning to have avoided this situation?
Select one
1608.
A previously unknown risk surfaces on a project and creates an issue that is estimated to cost $50,000. The project manager submits a change request to adjust the schedule baseline and uses the already approved contingency reserves to address the cost. What did the project manager do wrong?
Select one
1609.
You are establishing the relative priorities of individual project risks that have been identified earlier in the project. Which of the following tasks are you least likely to perform?
Select one
1610.
A project manager is facilitating a first brainstorming session to identify individual risks as well as sources of overall project risk. The meeting attendees are struggling with the task, and the meeting is becoming unproductive. What action might the project manager take to get the meeting back on track?
Select one