2,934 New PMP Id 1028 project management is concerned with managing which type of project Questions & Answers with explanation
1581.
Services are still being billed to the project even though no additional services are required or requested. What is the best option for the project manager to take?
Select one
1582.
A project has been initiated to search a large area for debris from an explosion of a failed prototype. The project is now in planning, and there is a debate among the team members on the type and quantity of resources needed to complete this activity. What should the project manager do first?
Select one
1583.
An international project is entering its final phase. Some work in this phase must be done in the foreign country. Unsure if company policy requires a full-time employee onsite for project work in that country, which project artifact should the project scheduler reference?
Select one
1584.
The project has to produce 10,000 new parts. The inspection points and their frequency along production must be determined. The part specifications and inspection modes to be used also need to be decided. In which process are these project plans defined?
Select one
1585.
A new project manager is brought on the project. She wants to understand the process by which this particular project formally accepts deliverables. Which of the following will she have to reference?
Select one
1586.
A dashboard viewable by all project stakeholders displays various statuses using the industry standard of red, yellow, and green colors. Throughout project execution, to meet the needs of the project and some of the project stakeholders, the project manager has been adding more colors to reflect additional statuses. This situation has created confusion among some of the stakeholders over the status naming conventions and meanings. What should the project manager do?
Select one
1587.
The updated version of the product is to be at the customer's location by the end of the week, but the team realizes they will be unable to complete the deliverable by then. The project manager and the team have looked for solutions to resolve this issue but there is nothing to avert missing the deadline. The deployment team who is supposed to install the product at the customer site is under a lot of stress to meet their deadline and are going to be furious that the update will not be there at the end of the week. What is the project manager's best action?
Select one
1588.
A project team member runs an earned value analysis (EVA) report. There is an unexpected spike in actual costs over the last three weeks. The team member shows the report to the project manager and based on her analysis presents four possible reasons for the spike. Which reason is most probable?
Select one
1589.
The project is nearing its end. The executives are anxious to assign the project manager to other projects. However, before moving on, the project manager has to deliver the final product to the customer. What should the project manager do first?
Select one
1590.
You are developing a project management plan for a project that is part of a program. You have just been informed that a new procedure has been added to the program management plan. The procedure requires that all changes that exceed $10,000 in cost have to be reviewed by the change control board (CCB). What should you do?
Select one