New PMP Question & Answers with explanation
Analogous Cost Estimating is which of the following?
Select one
Although the business value is unique to each organization, each organization strives to attain business value for its activities. Which of the following does NOT create value for an organization?
Select one
What does it mean if the Earned Value is equal to Actual Cost?
Select one
The Cost Management Plan is an output of the Plan Cost Management process. This plan is then integrated with other project plans in which of these processes?
Select one
A project was estimated to cost $200,000 with a timeline of 10 months. Due to a shipment delay, the schedule was slightly delayed. However, this was made up by shipping the first batch of materials for the project by air. The net result was that there was some additional cost in the project. At the end of the second month, the Project Manager reviews the project and finds that the project is 20% complete and Actual Costs are $50,000. The Estimate to Complete (ETC) for the project would now be:
Select one