New PMP Question & Answers with explanation

A project manager is aware of two critical, high-impact risks that must be addressed immediately. However, the necessary resources to address the risks are already committed to another project with critical deliverables. What should the project manager do?
Select one
A project manager is preparing the monthly project status report. Some new risks have been identified that could impact important key milestones. What should the project manager reference before presenting this new risk information?
Select one
A project risk budget was approved that only considered high-impact/high-potential risks. During project execution, a risk with high impact but very low potential occurs. While it is in the risk register, it is not in the budget. What should the project manager do first?
Select one
Signs of a potential economic recession were present during the planning stages of a large construction project. The risk of the recession was assigned as low probability and high impact, with an expected duration of 6-12 months. Soon after the project begins, the recession occurs and impacts the project as expected. After six months, the duration of the recession's impact is changed to 24-36 months. What should the project manager do?
Select one
A final deliverable will not be completed on time, which is delaying project closure. What should the project manager do next?
Select one