2,936 New PMP Questions & Answers with explanation

1571.
Not all team members are properly checking out resources used in the project. What is the best option for the project manager?
Select one
1572.
A key stakeholder has been resistant to the project's objectives, and the support of this stakeholder is vital to the success of the project. The project manager has employed various engagement strategies which have been ineffective and needs to determine the underlying reason that stakeholder engagement is not having the planned effect. What should the project manager do next?
Select one
1573.
You are assigned to a software development project, and you are conducting a product review with an important client. Although the deliverables were previously verified, the client detects a defect and rejects one of the deliverables. What should you do?
Select one
1574.
A company has been awarded a software development project which requires the development team to work at the client's office. The client has assigned each developer a cubicle from which to perform their work. During a daily standup meeting, a developer states that the team members are too isolated and colocating the team in a war room would increase productivity and quality. What should the project manager do first?
Select one
1575.
You are conducting the source selection analysis for an office building renovation project. One project requirement involves setting up the WiFi system once the hardware has been installed. The value of this procurement is relatively small, and you have decided that a full selection process does not make sense. With three prospective vendors listed as pre-approved sellers, what is the best course of action?
Select one
1576.
An apartment building construction project is currently in the planning stage. The project manager has decided to use analogous estimating to create the resource requirements and resource breakdown structure. What should the project manager do first?
Select one
1577.
A project manager is in the process of creating the quality management plan for a product development project. Currently, the project manager needs to understand and then estimate the cost of quality for a particular process. What is the best course of action?
Select one
1578.
You are in the process of developing an approximation of the monetary resources needed to complete project work for a large-scale multinational project which will take at least seven years to complete. Your previous projects have all been domestic with short timeframes. As part of the process you are currently performing, what might you need to do differently compared with your past projects?
Select one
1579.
A project manager is developing a cost management plan and needs to determine the best source of funding for a project that is dictated by a legal requirement. The cost of capital is estimated at 9.7% for non-dividend paying equity, 6.7% for debt, and 5.1% for self-funding. The NPV of the project is $500,000 with an opportunity cost of $750,000. What is the project manager's best course of action?
Select one
1580.
Your company was recently awarded a software development project, and you have just completed the scope management plan. The sponsor reviews the plan and states that the client specified the use of Scrum, while the plan indicates a waterfall approach. Which component of the project management plan did you most likely overlook while developing the scope management plan?
Select one