2,934 New PMP Questions & Answers with explanation

1591.
During a project's review, an executive states the project manager failed to forecast future outcomes based on past results, review how other projects addressed the similar issues, and analyze alternative solutions to issues. What has the project manager most likely overlooked with his intuitive manner of running the project?
Select one
1592.
As a project manager for a small university, you are currently in the process of selecting a vendor to develop a textbook and other training materials for a new course. Several vendors are interested in bidding on the contract. During a bidder conference, one of the prospective suppliers asks about ownership of the intellectual property that will be created from the project. Which project document should have this information at this stage of the project?
Select one
1593.
A team member has been tasked to send the request for proposal (RFP), source selection criteria, and procurement statement of work (SOW) to potential sellers. The documentation is stored digitally on the corporate computer network. Which folder from the project directory is most likely to include these documents?
Select one
1594.
Wendy is a project manager for an IT data center installation in a country that recently established independence. The country is in a strategic location for fiber optic communications, but the political climate is highly unstable. In order to keep the data center in the country but avoid unnecessary influence from the political dynamics, Wendy has negotiated with the U.S. Department of State to establish the data center in the basement of the U.S. Consulate in the capital city. This is an example of:
Select one
1595.
Tom is a project manager for a large software project. During project risk planning, Tom and his team are trying to decide whether to invest $10 million to develop new software or to instead invest $5 million to upgrade the existing software. The team is uncertain how strong demand will be for their product and, therefore, must account for this uncertainty in their analysis. What would be the best tool for the project manager to use in this case?
Select one
1596.
John is the project manager for a large construction project. He has just completed a Monte Carlo analysis simulation when he learns from a team member that some of the cost estimates used in the simulation were incorrect. John is highly risk-averse and concerned about this issue, so he meets with his team to discuss options for how to move forward. Based on this information, which choice below best describes what the team would likely do with the results from the Monte Carlo analysis?
Select one
1597.
As part of project planning, you and your project team are developing a comprehensive list of individual project risks and sources of overall project risk. You want to analyze the validity of assumptions and constraints to determine which pose a risk to the project. Which technique will be the most helpful for you?
Select one
1598.
As a project manager, you will need the assistance of other stakeholders in order to identify the risks associated with your project. You want to determine who are the individuals that might participate in the process of identifying risks to the project, as well as those who are available to act as risk owners. Where should you look?
Select one
1599.
A project to build a new water treatment plant is in the planning stage. The project manager is starting the project management process of Plan Risk Management. The project sponsor is risk averse, and this will affect the risk management plan. In preparing the risk management plan, the project manager is seeking a high-level understanding of the project description and boundaries, high-level requirements, and risks. Where is the best place for the project manager to find this information?
Select one
1600.
You are the project manager for the construction of a new thin-crust pizza vending machine. You take all the information gathered in the project management plan to date and begin to develop a project schedule. When you reach the activity labeled as 6.5.3, you are unsure if a refrigeration specialist is needed for the installation of the cooling mechanism for the pizza dough. What project document would you reference in order to get information on the resources required for installing the cooling mechanism?
Select one