2,936 New PMP Questions & Answers with explanation

2141.
The best practice to gather and document lessons learned is during weekly progress meetings. The agenda can have a lessons-learned brainstorming item at the end of these meetings. You can ask team members to put forward their recommendations, but it is always better to adopt a more structured way to gather lessons learned. Which of the following approaches will ensure you capture important lessons learned on your project?
Select one
2142.
You have recently joined an organization as the procurements manager. You have just received an invoice from a contractor. Some of the items from the invoice are as follows: EV of work completed to date: $50,000. AC of work completed to date: $40,000. Total costs reimbursed by the buyer to date: $35,000. If the contract between the buyer and the contractor is a CPIF contract, what is the total value payable to this contractor? (Assume that the contract allows for a 10 percent fee over net payable whenever CPI > 1).
Select one
2143.
To control the schedule, a project manager is reanalyzing the project to predict project duration. This is done by analyzing the sequence of activities with the least amount of flexibility. What technique is being used?
Select one
2144.
David’s project is currently in difficult times, and the project stakeholders are not happy with the project updates they receive. In a meeting with the project sponsor, David said the stakeholders’ attitude is irrational since he personally ensures that all project communications are accurate and timely. Mary, the project sponsor, advises David that he needs to go the extra mile in managing the stakeholders rather than just managing the project communications. What does Mary mean?
Select one
2145.
The Executive VP of Finance has informed you that you will be the project manager for an energy audit the company is performing in order to save expenses. He has assigned you to identify the stakeholders and to start documenting the high-level assumptions and constraints. Your project is in what stage?
Select one
2146.
While rating a proposal, one of the requirements was: "The proposed project manager needs to be a certified Project Management Professional, PMP®" This is an example of:
Select one
2147.
While reviewing project procurement and accounting records for your project, you discover there is a pattern of unauthorized expenses by a specific resource. These expenses are not within the scope of the project and were somewhat camouflaged within a number of large and complicated expense reports. What do you do?
Select one
2148.
The project management processes communicate with each other through their inputs and outputs. Which of the following outputs of the Direct and Manage Project Work process is a prime input of the Monitor Stakeholder Engagement process?
Select one
2149.
Linda has been assigned to establish a PMO in her organization. Linda believes this project cannot succeed unless all the key project stakeholders support the project. She also believes she needs to pay special attention to stakeholder management to ensure success of this project. First, she needs to develop her stakeholder register. To produce the project stakeholder register, which of the following processes must Linda start?
Select one
2150.
Your team has built an exotic sports car for a wealthy client. The project team verified every deliverable against the quality requirements, and the client accepted. Now the project manager is arranging for the car delivery. This is part of which process group?
Select one