2291.
You manage the construction of a new airport in your home country. Since your organization does not have experience deploying the sophisticated air-traffic control system, you outsourced this to a specialist organization. PMBOK’s Procurement Management knowledge will help you successfully administer this deal; however, for the supplier of the system, all the PMBOK processes will apply since this will be a complete project for the supplying organization. Which of the following will be a common denominator between your project and the supplier projects?
Select one
2292.
You have recently taken over a project as the project manager. The project is midway through execution, and most of the project work has been subcontracted. You have just found out that one of the subcontractors, who was responsible for all demolitions, has been paid 50 percent of the subcontracted value, but he has delivered only 25 percent of the required works. Upon investigation, you learned that all the payments are in line with the signed contract between the two parties and the subcontractor’s work is compliant with the contract specifications. You are annoyed because this does not give you enough control over the subcontracted works. Which of the following is not an appropriate thing to do at this stage?
Select one
2293.
Stakeholder notifications must be archived for future reference. Whenever the Manage Communications process produces a stakeholder notification, the notification must be:
Select one
2294.
A Work Breakdown Structure (WBS) dictionary supports the WBS and is a companion document to the WBS. Which of the following is not included in the WBS dictionary?
Select one
2295.
The State of New York has contracted with your company to provide a claims payment system for Medicaid benefits. In the contract, a clause states that the State of New York can review your work processes and deliverables. This is an example of:
Select one
2296.
Your project is nearing completion, but a previously unidentified risk has arisen, and it could significantly affect one of the project deliverables. What do you do?
Select one
2297.
James is currently managing a software upgrade project. He has recently identified and analyzed his key project stakeholders. He is now searching his organizational process assets for a template with which he can update the results of this analysis along with the planned strategies required to engage the stakeholders effectively. Which of the following should he search for?
Select one
2298.
As a project manager based at the customer location for a performing organization, you build rapport with a customer manager. As the project progresses, the manager asks you to make certain changes to the project scope and wants this handled on an informal basis. You should:
Select one
2299.
If you had an experience with a particularly well or poorly performing vendor, what is the correct way to document this experience for future projects?
Select one
2300.
What BEST describes the role of the project team members?
Select one