2,934 New PMP Questions & Answers with explanation

2341.
Which of the following is not an organizational process asset used during the Plan Resource Management process?
Select one
2342.
Which of the following is not a Risk Diagramming technique?
Select one
2343.
The Cost of Quality principle includes:
Select one
2344.
The most recent analysis of Microcorp's new fabrication facility renovation project shows a CPI value of less than 1.0. What does this indicate?
Select one
2345.
Robert is managing a road construction project. Due to unseasonal weather conditions, the team productivity might be above or below target. This is an example of:
Select one
2346.
Which of the following is NOT a valid WBS creation approach:
Select one
2347.
Project performance measurements assess the magnitude of variation from the original cost baseline. Once the degree of cost variation is known, what step is performed next?
Select one
2348.
A software team tracing the root cause of an application failure can use this to help determine the cause(s) of the failure:
Select one
2349.
What is a control chart?
Select one
2350.
Which of the following tools can enhance the visibility of traditional written project plans and other documents to provide a real-time overview of the project status?
Select one