2,934 New PMP Questions & Answers with explanation
2501.
A business is considering more than a dozen infrastructure upgrade projects. These projects, once delivered, will add to the organization’s overall performance but will not contribute to any of the revenue streams. Prior to initiating any such project, the value of the project to the organization must be determined. Which of the following is the most important factor to consider in such a scenario?
Select one
2502.
If a project manager believes that a particular subcontract needs to be terminated, which of the following can provide guidance on the contract termination procedure?
Select one
2503.
The technique most commonly used by project management software packages to construct a project schedule model is:
Select one
2504.
Which of the following defines the total scope of the project and represents the work specified in the current approved project scope statement?
Select one
2505.
Change control tool selection should be based on the needs of the project stakeholders, including organizational and environmental considerations and/or constraints. Which of the following is not a key change management consideration while selecting an appropriate change control tool for a project?
Select one
2506.
Which of the following items needs to be kept in mind when relying on risk identification checklists?
Select one
2507.
As a project manager, you are analyzing the costs incurred in a project. Which of the following costs cannot be classified under cost of nonconformance?
Select one
2508.
You have just joined a new organization as a project manager. You have heard a number of rumors about the procurement manager having possible underhanded dealings with suppliers. However, you have no proof these rumors are true. Your project requires a large number of dump trucks. Company policy mandates that all purchases go through the procurement department rather than the department employees. The value of the dump truck purchase is US$395,000, and the contract went to a supplier your company regularly uses. Shortly after taking delivery of the dump trucks, you learn the procurement manager is driving a new car. What should you do?
Select one
2509.
You are managing an electronic chip design project for a customer. There are a number of engineers and subject matter experts from the customer’s organization that have been assigned as resources to the project plus several additional design engineers that your company has supplied. All the engineers were involved in the development of a prototype chip, an extremely time-consuming and expensive process. Upon the completion of the prototype, you submit it for review to ensure there are no patent infringement issues with the design. However, the review determines there are several issues that could result in an intellectual property dispute with the patent owners should the prototype design be released commercially. Resources from your company developed the affected prototype elements, as well as from your customer’s organization. What should you do?
Select one
2510.
The RACI chart is an example of a responsibility assignment matrix (RAM). The letters R and C in “RACI” stand for:
Select one