2,934 New PMP Questions & Answers with explanation
431.
Which of the following best describes individual project risk?
Select one
432.
What do functional requirements describe?
Select one
433.
A project manager learns of a recent issue that has been identified while running cable underground. The issue is deemed to be minor, so the project manager emails the project sponsor to ensure she is kept informed of all activities, as requested. What type of communication method did the project manager use?
Select one
434.
A project manager is working with a risk manager to prioritize individual project risks. What project management process is associated with this activity?
Select one
435.
You are a project manager for Lightning Bolt Enterprises using a hybrid model to manage projects. Your new project involves the research and development of a new type of rechargeable battery. The project objectives should include which of the following?
Select one
436.
Roshoud is the VP of customer operations for Galactic Kidz and the project sponsor of the latest project, called Project G. He sits down with Sally, the project manager, to discuss how they will respond to the risks identified. For one risk in particular, he asks Sally to facilitate the purchase of insurance to protect against a liability. What type of risk response is this?
Select one
437.
Yasmin is the project manager of a project that will produce a new line of widgets for the company. She guides the project team in defining the project requirements in detail before moving into production. Because of compliance requirements that must be met, she maintains a rigid change control process for changing requirements. What method is Yasmin using to manage the project?
Select one
438.
After concluding the sprint, the Scrum master, product owner, and team members come together to evaluate the overall progress and work completed and to review any lessons learned. This describes what type of meeting?
Select one
439.
Which of the following best describes how Planning activities are performed in a highly adaptive (Agile) life cycle?
Select one
440.
Kaylee is a risk manager working in collaboration with Alyssa, a project manager, and both work for a top healthcare company. They partner to facilitate a session to determine how the project team can best exploit an opportunity that was recently identified. Kaylee and Alyssa are performing activities associated with what project management Knowledge Area?
Select one