767 New PMP Process Questions & Answers with explanation

271.
A project has the highest probability of completing successfully at which stage of the project?
Select one
272.
Direct and Manage Project Work, Manage Quality, and Conduct Procurements are processes belonging to what project management process group?
Select one
273.
Which of the following best describes the purpose of carrying out activities associated with planning stakeholder engagement?
Select one
274.
Chu is a Scrum master working closely with Rita, the product owner, to release the latest version of a digital music device. The team is currently in their fourth sprint. Chu joins the team near the coffee machine, where their Kanban board was placed, to meet for 15 minutes and talk through what each team member completed since yesterday, what they will complete, and any obstacles that may get in the way of their commitment. What activity is Chu and the team engaged in?
Select one
275.
You use a predictive approach to managing projects and have just completed your cost baseline. Next, you begin working on determining funding requirements. Which of the following is true?
Select one
276.
Which of the following best describes overall project risk?
Select one
277.
Alyssa is a project manager tasked with managing an infrastructure project that will consolidate five data centers into one. She is currently facilitating the estimating process to calculate the duration of the project’s activities. Alyssa knows that she has reliable information and is therefore planning on using an estimating technique that will yield a highly accurate estimate with minimal effort expended. What estimating technique is she planning on using?
Select one
278.
Roshoud is the VP of customer operations for Galactic Kidz and project sponsor of the latest project, called Project G. He sits down with Sally, the project manager, to discuss the current budget estimate. Roshoud expresses his concerns to Sally over the budget being far greater than originally anticipated and asks her to course-correct. What produces the greatest expense on most projects?
Select one
279.
You are working on the communications management plan for your project and have considered the timing and need for updated information by you and your four stakeholders. Your organization has modern, up-to-date technology that your stakeholders and staff have used before, so you anticipate that supplying the information and updates to your stakeholders and team members will be a breeze. Which of the following is true?
Select one
280.
Kaylee is a risk manager working in collaboration with Alyssa, a project manager, and both work for a top healthcare company. They currently follow a feature-driven development approach to managing software-based projects. They work together to analyze risk, noting that of the 20 risks identified, 5 are deemed to be low priority. Where will these risks be documented?
Select one