767 New PMP Process Questions & Answers with explanation
661.
Mandatory dependency is also known by what other name?
Select one
662.
Which type of estimating technique can have a high level of accuracy?
Select one
663.
Carina is a principal project manager of You’ve Got Dogs, a specialty company that creates custom dog apparel and toys. She has just obtained approval of the project management plan and is about to publish it to the project team. What process group are the activities she is performing associated with?
Select one
664.
Sally and Joe are two project managers working in the corporate offices of a popular fast-food franchise. They are both studying for their PMP® certification and are having a discussion on the WBS. Sally is confused and asks Joe to describe what the WBS contains. What is Joe likely to respond with?
Select one
665.
You are sequencing activities and have just begun to identify dependencies. What can you use to help get you started quickly?
Select one
666.
Your project includes a new manufacturing technique that requires knowledge of chemical engineering to perform one of the services required in the project management plan. The service was performed, and as a result, an approved change request has been submitted. Which of the following statements is true?
Select one
667.
Nicolas is the project manager of a project that has been described as revolutionizing the mobile fitness tracking industry. He recently used his negotiation skills to achieve the support and agreement of two functional leads involved in his project. As part of his approach, he references the plan that outlines strategies and actions documented to manage specific stakeholders. What document did Nicolas reference to get this information?
Select one
668.
According to the PMBOK® Guide, this output of the Manage Stakeholder Engagement process is used to promote communication with stakeholders.
Select one
669.
There are 10 stakeholders within your project. As the project manager, you must therefore manage 45 communication channels. Two additional stakeholders have been added. How many more channels of communication must you manage?
Select one
670.
All of the following are true regarding project phases except for which one?
Select one