767 New PMP Process Questions & Answers with explanation

671.
The project team recently participated in a working session to examine and document the effectiveness of risk responses in dealing with overall project risk. What is this working session, or meeting, called?
Select one
672.
A project manager meets with the project team to estimate the duration of activities identified to date. The project sponsor recently guided the project manager to present her with a duration estimate for the project that contains a high confidence level. What estimating technique is the project manager likely to use, assuming that the necessary information is available?
Select one
673.
Who is responsible for determining which processes within each process group are appropriate for the project?
Select one
674.
Given the following information, is the project schedule ahead of or behind what was planned for this period? EV = 95, PV = 85, AC = 100.
Select one
675.
You are working on a critical project for your organization. The CEO has made it clear this is a top priority. One of the key stakeholders on your project resigned, and her replacement started about three weeks ago. She does not make time for you or seem to have the same level of urgency regarding this project as the CEO. You are concerned with overall project success and want to efficiently manage the processes involved with this project. Which of the following addresses this situation?
Select one
676.
Cost plus incentive fee, cost plus award fee, cost plus percentage of cost, and cost plus fixed fee are all other names for what contract type?
Select one
677.
Availability, experience levels, interests, cost, and abilities of project resources are considered part of which input to the Acquire Resources process?
Select one
678.
All of the following statements are true about the Project Resource Management Knowledge Area except for which one?
Select one
679.
All of the following statements are true regarding the Manage Project Knowledge process except for which one?
Select one
680.
You are a project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor’s work involves digging the holes and setting the lamp poles in concrete. You’ve discovered the subcontractor’s work is not correct because the poles are not buried to the correct depth. You review the work and note gaps in the process and a lack of safety standards as a result of this error. Which of the following is true?
Select one