237 New PMP Quality Questions & Answers with explanation

21.
A project manager is leading a project to streamline the manufacturing process of modular homes. The project manager researches and discovers a set of technical guidelines that will make the homes easier and cheaper to manufacture without compromising quality. The team incorporates these guidelines by designing a new modular home that reduces the total number of parts and uses more standard and multi-functional components. This is an example of:
Select one
22.
After taking over a project that is in the middle of execution, you are looking for information about the quality management issues that have been escalated by the team and any corrective actions that have been recommended and/or implemented. What should you do?
Select one
23.
During an inspection of a project deliverable, the team detects the same defect in the deliverable that has already been identified during a previous inspection. The project manager is confused how this could have happened since a change request was approved to correct the defect. After discussing the issue with the team, the project manager learns that the team never implemented the approved change request. What could have helped prevent this situation?
Select one
24.
You are managing an engineering design project. The vendor has created 50 engineering drawings. Since the project is on a tight schedule and budget, checking every drawing for accuracy and completeness would be impossible. You direct the team to randomly select 20 drawings for inspection. This exercise can best be described as an example of:
Select one
25.
Which of the following helps a project manager determine possible causes of potential problems and actual problems?
Select one
26.
A project manager has to resolve two problems. Both problems can occur in a single trial. In this situation, what is the best action the project manager can take?
Select one
27.
You are the program level manager with several project activities underway. In the executing process group, you begin to become concerned about the accuracy of progress reports from the projects. What would best support your opinion that there is a problem?
Select one
28.
The project team has created a plan for how they will implement the quality policy. It addresses the organizational structure, responsibilities. Procedures and other information about plans for quality. If this changes during the project. Which of the following plans will also change?
Select one
29.
All of the following are not examples of quality assurance except?
Select one
30.
A control chart shows that the last eight pipes produced were all less than average weight. You need to inform management that there is a problem because the situation violates the:
Select one