100 New PMP Schedule Questions & Answers with explanation
31.
Which of these processes is not a Project Schedule Management process?
Select one
32.
During a presentation to management, you want to display the project schedule with only the key deliverables displayed. What is the correct tool for this purpose?
Select one
33.
Which of the Project Schedule Management processes involves identifying and documenting dependencies among schedule activities?
Select one
34.
You are the project manager responsible for building a 100,000-squarefoot data center. One of the scheduled activities in your plan is to install the Computer Room Air Conditioning (CRAC) units. However, before beginning the installation of the units, a raised floor must be installed for the units to bolt to. This is an example of what type of dependency?
Select one
35.
Which of these is accurate regarding the Develop Schedule process?
Select one
36.
Predicting future performance based on historical events is called ___________.
Select one
37.
Which of the following is NOT a valid statement regarding the critical path method?
Select one
38.
Linda is a first-time project manager and is analyzing a project schedule. She intends to apply resource leveling, and she has the following guidelines on Resource Leveling. Which of these four statements is incorrect?
Select one
39.
In which of the following situations would it be better to avoid using Analogous Estimating?
Select one
40.
Mary is a project manager for an infrastructure upgrade project in a government agency. She realized recently that a critical scheduled task exceeded its deadline, and the stakeholders are aware of it. The resource manager has permitted Mary to use three more resources to work on and complete the delayed task. Although the three additional resources prove helpful, Mary is still concerned about the task because:
Select one