100 New PMP Schedule Questions & Answers with explanation

61.
Which of the following is an output of the Define Activities process?
Select one
62.
While planning the schedule for your project, you frequently refer to the project calendar. The project calendar is:
Select one
63.
You are attempting to estimate the resources required to assemble the server racks in the new data center you are building. It has occurred to you that you may be able to compress the schedule if you use power tools instead of hand tools to build the racks and if you employ individuals who have worked on this brand of rack in the past. According to PMBOK, considering multiple options for estimating is an example of what type of resource estimating technique?
Select one
64.
During a work breakdown structure meeting, you have decomposed the deliverables into work packages and created your WBS dictionary. However, you now want to decompose the work packages to assist you in estimating, executing, and controlling the project. These decomposed work packages are:
Select one
65.
A technique that calculates multiple project durations with different sets of activity assumptions and variables is:
Select one
66.
The senior analyst on a project came up with Activity Duration Estimates as follows: Activity A: 10 days + a lag of two days; Activity B: 1 week + a lead of three days. The project manager who reviewed these estimates raised some objections to them. What would they most likely be?
Select one
67.
While sequencing activities for a project, the project management team applied certain discretionary dependencies. This was based on their knowledge of best practices within the project application area. What is the potential risk involved in using such dependencies?
Select one
68.
Activity attributes extend the description of the activity by identifying various components associated with the activity. Typically, how many attributes are associated with each activity?
Select one
69.
You are working as a project manager for a wind-powered vehicle manufacturing project which is in its planning phase. You carefully gathered all your requirements from your key stakeholders and prepared a system requirements specification and project requirements specification. While presenting your specifications to the project team, an enthusiastic project team member started talking about the duration estimates for each activity. Which of the following statements indicates your response to your team member?
Select one
70.
In a small office construction project, the following activities are scheduled in sequence. i) Digging and pouring footings: five days. ii) Working on the slab and pouring: three days. iii) Framing the floor: five days. iv) Wall framing: four days. v) Roof framing: six days. vi) Insulation and drywall: seven days. vii) Interior doors and trim: three days. viii) Hardware and fixtures: two days. What is the minimum time to complete the project if all activities are on a critical path except activity viii, and activity iii is delayed by one day?
Select one