100 New PMP Schedule Questions & Answers with explanation

51.
Which of these precedence relationships is most commonly used in the Precedence Diagramming Method?
Select one
52.
If you want to compress a project schedule, what are two of the recommended alternatives to consider?
Select one
53.
Most project management software packages use a method of constructing a project schedule network diagram known as:
Select one
54.
A project manager estimates the work to be accomplished in the near term in detail at a low level of the Work Breakdown Structure (WBS). He estimates work far in the future as WBS components that are at a relatively high level of the WBS. What is this technique called?
Select one
55.
A technical team can begin to edit a large document 15 days after it begins writing it. What kind of dependency would this represent?
Select one
56.
Which of the following is accurate regarding the Estimate Activity Resources process?
Select one
57.
In a project, Activity A has a duration of four days and begins on the morning of Monday the fourth. The successor Activity, B, has a Finishto-Start (FS) relationship with A. The Finish-to-Start relationship has two days of lag, and Activity B has a duration of three days. If Saturday and Sunday are non-working days, which of the following statements is true?
Select one
58.
A project manager needed to shorten a project schedule and decided to employ crashing, a schedule compression technique. Which of the following activities would not be an example of crashing?
Select one
59.
A project manager is estimating the project duration and finds that the only information available to him is a previous project that was quite different from the current one. However, some portions of the previous project were similar to the current one. Which of the following tools is the project manager likely to use to compare current project's activity durations with the similar previous activities?
Select one
60.
Jane is worried about her project because many of her tasks are moving slowly, and two critical tasks may slip. She conducts a thorough resource analysis and finds out that there are five people who will be free next week. She would like to assign those people to finish her tasks early and prevent the project completion date from slipping. This is an example of:
Select one