119 New PMP Scope Questions & Answers with explanation

21.
Which of the following techniques can be used to control scope within a project using a predictive life cycle?
Select one
22.
You work for a company that writes billing software programs for the communication industry. Your customer is located in a country that limits the number of foreigners allowed into the country. You identify this risk in your risk management plan. The critical point during the project is installation and setup. You have assessed the risks and are using the Perform Qualitative Risk Analysis process. Which of the following tools and techniques will you use to determine the potential effect on the project objectives (such as time, cost, scope, or quality) and determine the likelihood of the risk occurring?
Select one
23.
According to Edward de Bono, what type of alternatives analysis can be used to determine a project’s scope?
Select one
24.
Which of the following are components that make up the scope baseline?
Select three
25.
You are a project manager for Lightning Bolt Enterprises. Your new project involves the research and development of a new type of rechargeable battery. The project objectives, as documented in the project charter and used in creating the project scope statement, should include which of the following?
Select one
26.
A project manager is performing activities associated with monitoring and controlling the scope of the project. What key information can they use in conjunction with the plan to help them get started?
Select one
27.
You are the project manager for Ooh La La Beauty Products. Your project concerns developing a new line of bath products. You also serve on the CCB, which has just approved a scope change. You know that all of the following statements are true except which one?
Select one
28.
The project sponsor asks the project manager to validate that the product scope has been met. What will the project manager use to measure the completion of the product scope?
Select one
29.
David is a project manager working for a prominent book publishing company. As the most senior project manager within the organization, he often gets the most complex project assignments. For this reason, the PMO manager assigns David to manage a project for a sponsor who is notorious for scope creep. Knowing this, David is likely to place greater emphasis on what project management process?
Select one
30.
Alyssa is a project manager tasked with managing an infrastructure project that will consolidate five data centers into one. She pulls together a core set of experts who have worked on similar projects to discuss how scope should be managed. What tool or technique is Alyssa using?
Select one