119 New PMP Scope Questions & Answers with explanation
81.
Which of the following graphical techniques visually depict the product scope by showing a business system and how other systems interact with it?
Select one
82.
In predictive projects, the scope baseline for the project is used to analyze a project’s scope performance. On the other hand, projects with adaptive lifecycles use:
Select one
83.
The key difference between Validate Scope and Control Quality is:
Select one
84.
Due to the unexpected release of a similar product from a competitor, the Widgets International executive team has stepped up the pressure on the product team to release the Widget product three months earlier. The project manager uses what technique to shorten the schedule but maintain the project scope?
Select one
85.
Your project team is having a dispute with a vendor about whether a specific task is within the project’s scope. The scope statement does not provide implementation-level details that could resolve this dispute. There is no WBS, however, because the project sponsor insisted that the project be started right away without pausing to create standard project planning documentation. Who is at fault?
Select one
86.
A project is contracted on a Cost-Plus-Fixed-Fee (CPFF) basis with a fee of 10 percent of estimated costs. The estimated cost is US$50,000. If the project comes in at US$75,000 with no changes in project scope, what would be the total cost of the contract?
Select one
87.
The sponsor of your facilities upgrade project has left the company to join another organization. Several weeks later, you are reviewing the business case for the project, and you find that there are several inconsistencies between what is stated in the business case and what is described in the project scope. Further research shows that the business case as a whole is based on inaccurate information. What do you do?
Select one
88.
Mark is managing a telecom network deployment project. The buyer of the telecom network is an external entity. Recently, the customer requested that all future project updates be posted to their information system automatically. In order to implement this, the project team needs to customize their project management information system so it can be integrated with the customer’s information system. This is a new customer requirement that was not a part of the original project’s scope. What should the project manager do?
Select one
89.
An experienced project manager was assigned a project of small scope. Which of the following could be true of the project?
Select one
90.
Analysis of the scope performance resulted in a change request to the scope baseline. Change requests can include all the following except:
Select one