2,934 New PMP Id 1028 project management is concerned with managing which type of project Questions & Answers with explanation

1561.

A project manager for a software development project has collected the work performance data and used the requirements documentation and requirements traceability matrix to generate the work performance information regarding variances in the project work compared to the baseline. What process is the project manager performing?

Select one
1562.

As part of the process to develop the scope statement for the project you are leading, you specify the deliverables for the project, include the requirements under which the deliverables will be accepted, and explicitly state what is out of project scope. What should you do next?

Select one
1563.
Sharing of project information is of utmost importance to the organization. Project knowledge is shared on multiple systems, services, and apps. The array of locations is becoming overwhelming for some of the project team members. What is the best option for the project manager to manage the project knowledge in this situation?
Select one
1564.
The project manager and the team decide that the project will be divided into five-week iterations with two weeks in between for retrospectives and iteration planning. Where is this documented?
Select one
1565.
The project sponsor is concerned about possible ethics violations between the project and vendors. What independent review can the sponsor order?
Select one
1566.
In a pharmaceutical project, human trials are to start soon. The CEO is thrilled about the success of the trials up to this point. She announces that the size of the patient pool for the trials should double from the one originally planned and results tracked in the new system launching this week. What should the project manager do first?
Select one
1567.
In a pharmaceutical project, human trials are to start soon. The CEO is thrilled about the success of the trials up to this point. She announces that the size of the patient pool for the trials should double from the one originally planned and results tracked in the new system launching this week. What should the project manager do first?
Select one
1568.
Stakeholders are not sure what to do about the multiple failures the project has been experiencing recently. Changes need to be made quickly otherwise the project may be terminated as consistently missing its objectives. What should the project manager do first?
Select one
1569.
Not all team members are properly checking out resources used in the project. What is the best option for the project manager?
Select one
1570.
A key stakeholder has been resistant to the project's objectives, and the support of this stakeholder is vital to the success of the project. The project manager has employed various engagement strategies which have been ineffective and needs to determine the underlying reason that stakeholder engagement is not having the planned effect. What should the project manager do next?
Select one