2,934 New PMP Id 1028 project management is concerned with managing which type of project Questions & Answers with explanation
621.
You are a fabulous project manager, and your team thinks highly of you. You are well respected by the stakeholders, management team, and project team. When you make decisions, others follow your lead as a result of which of the following?
Select one
622.
Your team is dispersed and they are physically split between two buildings on opposite sides of town. As a result, the team isn't very cohesive because the members don't know each other very well. The team is still in the storming stage because of the separation issues. Which of the following statements are true regarding this question?
Select two
623.
You've promised your team two days of paid time off plus a week's training in the latest technology of their choice if they complete their project ahead of schedule. This is an example of which of the following?
Select one
624.
You are the project manager for a cable service provider. Your project team is researching a new service offering. They have been working together for quite some time and have a good understanding of the task at hand. They will not likely need any direction from you to complete this task. According to Blanchard, what type of leadership style does this describe?
Select one
625.
You are the project manager for a cable service provider. Your project team is researching a new service offering. They have been working together for quite some time and are in the performing stage of team development. A new member has been introduced to the team. Which of the following statements is true?
Select one
626.
You are the project manager for a cable service provider. Your team members are amiable with one another and are careful to make project decisions jointly. Which of the following statements is true?
Select one
627.
During a recent team meeting, you reached a resolution to an issue that's been troubling the team for several weeks. It turned out that there was a problem with one of the manufactured parts required for the project. Once this was corrected, the remaining production run went off without a hitch. You took responsibility for searching out the facts of this problem and implemented a change request to resolve the issue. Which of the following is true regarding this question?
Select one
628.
Your team is working on an agile project developing an app that alerts airline passengers to gate changes for their flights once they've checked in. They are having a difficult time understanding how the user stories work together toward the big picture. Which of the following should you do?
Select two
629.
You are in the Executing process and observing and gathering information on project elements such as schedule status, deliverables completion, lessons learned, KPIs, technical performance measures, and resource utilization. Which of the following statements is true regarding this question?
Select one
630.
You are considering using an agile approach to conduct your project. The organization's culture is open to new ideas and supports honesty and transparency. They use KPI measurements to evaluate success. Which of the following statements are true?
Select one