While developing the project schedule, you find that the completion of a successor activity depends on the completion of its predecessor activity. What is this dependency called?
Select one
A technical team can begin to edit a large document 15 days after it begins writing it. What kind of dependency would this represent?
Select one
A project manager estimates the work to be accomplished in the near term in detail at a low level of the Work Breakdown Structure (WBS). He estimates work far in the future as WBS components that are at a relatively high level of the WBS. What is this technique called?
Select one
Most project management software packages use a method of constructing a project schedule network diagram known as:
Select one
A hierarchical structure of project resources organized by category and resource type, used in planning, managing and controlling project work, is:
Select one