113 New PMP Integration Questions & Answers with explanation

11.
As a project manager, you are in the process of establishing a knowledge management system for your project. Which of the following actions will be the least beneficial in this process?
Select one
12.
A project manager is about to start planning a software development project. The project sponsor would like to review any project risks that have been identified at this point. Which document should the project manager recommend the sponsor to review?
Select one
13.
You are a project manager for a national consumer goods retailer. Currently, you are about to start the development of the assumption log for a project to build a new retail store. What should you do first?
Select one
14.
You are employed by a software development company as a project manager. Your company has a policy that a change control board (CCB) reviews all of the change requests for every project in your organization, and the CCB follows all the recommended activities outlined in the PMBOK® Guide. You and your project team do not serve as members of the CCB. Based on this scenario, which of the following activities might be performed by members of the CCB?
Select one
15.
A project manager is leading a process improvement project for a factory operation. Currently, the project manager and the team are performing the Monitor and Control Project Work process. Which of the following activities might the project manager and the team conduct during this process?
Select one
16.

You are managing a project in Alaska to extend an existing oil pipeline, and you are about to start project planning. Due to the large size of the project along with the regulatory and environmental considerations, the development of a detailed project management plan will be critical. As a starting point for initial project planning, what is the first thing you should do?

Select one
17.

Your company has just been awarded the contract for an important research project. The CEO of your company has asked you, as the project manager, to create the project charter and send it to her so that she can review and approve it. To create the project charter, you need the project's statement of work (SOW). What should you do?

Select one
18.
A business is considering more than a dozen infrastructure upgrade projects. These projects, once delivered, will add to the organization’s overall performance but will not contribute to any of the revenue streams. Prior to initiating any such project, the value of the project to the organization must be determined. Which of the following is the most important factor to consider in such a scenario?
Select one
19.
Change control tool selection should be based on the needs of the project stakeholders, including organizational and environmental considerations and/or constraints. Which of the following is not a key change management consideration while selecting an appropriate change control tool for a project?
Select one
20.
Mark is in the middle of a software development project. So far, the project has incurred a total cost of $50,000. If it is determined the project is no longer required, what would we call the cost incurred to date?
Select one