2,934 New PMP Questions & Answers with explanation

1431.
You are a project manager for a network cabling project for your organization. Your project team consists of six full-time employees and three contractors. They have all worked together on a previous project a year ago. You are new to the team. Which of the following is true?
Select one
1432.
You are in the process of facilitating a change control meeting. You review a change request that would double the scope of the project but would not yield a major increase in the project’s resulting benefits. You know that the submitter of the change request has a tendency to bloat a project’s scope without fully thinking through the impact, but as a result of their position in the company, their changes tend to be approved. You invite a financial analyst to the meeting to walk the team through the negative impact of the change request, and the team votes to reject the change. What type of power did you use?
Select one
1433.
A project manager managing a small project has a total of 12 active stakeholders. How many lines of communication exist?
Select one
1434.
You are a project manager with a new company. You started less than 30 days ago. Your boss has told you it’s urgent that resources are attained and assigned to the project as soon as possible. This is your top priority. You have both internal and external resources. You have two internal positions that will be full-time employees, but the positions are vacant, so you need to recruit for and fill these positions. You happen to have a good friend you’ve known for several years who also attends your local PMI chapter. He is well qualified and looking for a new position. You call him up and hire him on the spot. You will be hiring your external resources using a work order against a contract you have with a local staffing agency. Which of the following is true regarding this situation?
Select one
1435.
Your project is running behind schedule and over budget. The account manager of a supplier you’ve worked with before tells you that if you select them for a contract they are bidding on, they will throw in a free resource. Later that day, you meet with the vendor selection committee and see that the vendor ranks at the bottom of the stack. You select the vendor anyway to help the budget, even though it goes against the procurement policy. How may your actions be perceived?
Select one
1436.
You are managing a project on contract. Your bonus is contingent on the timely completion of the project. The project is behind schedule, but the remaining tasks are easy to complete and won’t take more than a week. Which of the following is the most appropriate response?
Select one
1437.
Three of your stakeholders have approached you regarding the difficulty they are having with one of your team members. This team member is making inappropriate jokes, continually interrupts others, and is argumentative and unwilling to listen to the stakeholders’ ideas. What is the offending team member lacking in this situation?
Select one
1438.
You are a project manager for Dakota Software Consulting Services. You’re working with a major retailer that offers its products through mail-order catalogs. It’s interested in knowing customer characteristics, the amounts of first-time orders, and similar information. At one of your first project meetings, you explain to the team that quality is the number-one priority with this project and you will immediately deal with any project results (and those who caused them) that are not in keeping with this goal. The last software company that worked with this retailer was terminated because the quality of the end product was unacceptable. You tell the team there will be rewards for those who meet the quality requirements of this project. You also tell them the guidelines for escalating issues with the retailer and instruct them there are to be no deviations from this process. You want to know about anything that has the potential to become an issue. You conclude the meeting and return to your office to write the next status report. Which of the following is true regarding this question?
Select one
1439.
One of your team members, Daniela, talks with you privately about a confrontation she just had with Noelle, another team member working on the same project. It seems they can’t agree on a fundamental business process needed for the project. They both think they are correct in their view, and each has set up a meeting with you, independently, to convince you of her position. Which of the following statements is true?
Select one
1440.
A project manager meets with the team to increase cultural awareness by conducting training on cultural norms relating to countries they will be closely engaged with. What activity is the project manager engaged in?
Select one