2,934 New PMP Questions & Answers with explanation
211.
While an activity on the critical path is being executed, the functional lead removes two project resources involved in this activity to support the resolution of a contingency situation. What should the project manager do?
Select one
212.
A new project manager joins a project during the delivery of a critical milestone. As this project has multiple stakeholders, the project manager needs to determine which stakeholders should receive information about the delivery. To what should the project manager refer?
Select one
213.
The day before manufacturing is to start, a project manager learns that the engineering design was not accepted by the end user. What should the project manager do?
Select one
214.
A project manager is developing the schedule management plan for a data center migration project. The project sponsor asks for a schedule that plans all tasks as soon as possible. The project manager is presented with possible network paths that will not violate schedule constraints. What leads and lags relationship should the project manager select?
Select one
215.
During a demo and review meeting, the progress report shows that an agile project is not on track. The project manager is surprised, because all work was purposely selected and sequenced to meet higher-level objectives. What should the project manager have done to prevent this miscommunication?
Select one
216.
A project manager is developing a project charter, but a key stakeholder is failing to provide information about the expected project benefits. What should the project manager do?
Select one
217.
At the end of an iteration, a team member tells the project manager that a planned task is unfinished because of an issue that appeared days ago but was unable to be resolved. What should the project manager do to prevent this type of situation in the future?
Select one
218.
A new team member joins a project. The project manager is highly disciplined and expects timely participation in weekly meetings. The new member comes from an organization with a liberal culture and, out of habit, is continually late for meetings. When asked why, the team member responds that they are busy working on deliverables, which they believe have priority. What should the project manager do?
Select one
219.
A stakeholder requests more frequent and detailed updates on the project's status. The stakeholder also expresses interest in helping with the project. What should the project manager do next?
Select one
220.
A new project will update the software version on the company's database. The core development team will attend technical training on the update to learn about its new functionalities. What should the project manager do to increase the quality of the team's technical training experience?
Select one